In the face of recent major breaks in the Transcanyon Water Line (TCWL), the National Park Service (NPS) and contractor Stronghold Engineering Inc. have accelerated work at various locations on the $208 million Grand Canyon National Park replacement project.
The stepped-up effort follows a series of recent failures that forced the park to suspend overnight accommodations on the South Rim for nearly two weeks while crews stabilized the system and conserved water for essential daily use services. It was the second time in 2025 and the third time in two years that the park was forced to stop hosting due to lack of water. In addition, since 2010 there have been more than 85 major breaks that have disrupted the water supply.
Currently, the project includes teams working on several fronts. They are installing new steel pipeline segments, building water treatment plants at the South Rim and Phantom Ranch, and developing a new helibase operations building. Work areas include the Bright Angel Trail, the North Kaibab Trail, the Phantom Ranch Delta, and several locations in the inner canyon accessible only by foot or helicopter.
“The project has significant phasing and sequencing elements to complete the full pipeline replacement at different locations based on the specific needs of each section,” says Daniel Fleming, project manager for the NPS Denver Service Center.
HDR Inc. acts as lead design engineer. GSE Construction is the subcontractor responsible for the construction of the booster pumping station and water treatment plants. Other subcontractors include Winegardner Masonry and Spear E Enterprises. Approximately 160 workers are on the project at any given time.
As the project owner, NPS does not allow Stronghold Engineering or other project team members to discuss the project publicly.
.jpg)
Water treatment plants are under construction at the South Rim and Phantom Ranch sites.
Photo courtesy of nps.gov
Why replacement is needed
The original TCWL was built in the 1960s from lightweight aluminum tubes that could be dropped into the barrel with aviation equipment available at the time. While the material reduced transportation challenges, “much of the existing pipe is surface-mounted and exposed to the elements,” Fleming says. “Factors such as extreme temperatures, falling rocks, the differential between the temperature of the pipes and the water, and the high pressures and velocities being transmitted through the system contributed to the ruptures.”
Breakages typically cost more than $25,000 to repair and take three to five days to fix. Some failures require extended conservation measures if several consecutive failures occur. Repeated outages have highlighted the need for a more durable and modern system capable of supporting millions of annual visitors.
Project officials say the overall design of the new water project involved about 10 years of testing, analysis, review and coordination to meet various state and federal public health standards, environmental laws, and historic and NPS resource management policies.
A major component of the replacement project is moving the water intake from Roaring Springs to Bright Angel Creek. This change will reduce the length of the TCWL by about seven miles and eliminate the segment with the highest concentration of breaks.
The project also includes a new steel pipe system along the inner canyon corridor; sliding of existing distribution lines at Havasupai Gardens, Cottonwood Campground and Manzanita Rest Area; and the installation of energy and communications ducts along the route of the gas pipeline.
“In traditional projects, all utilities are installed in the same trench at the same time. Here, canyon limitations prevent that. Each utility requires a separate excavation.”
—Daniel Fleming, Project Manager, National Park Service
Below Plateau Point, crews are also hand-cutting a 5-foot-wide trench on steep slopes for the new waterline. A second trench for energy and communications will follow.
The new pipe is mainly made of steel, selected for its durability and ability to withstand high pressures and environmental stresses. FlexSteel pipe is used only between the South Rim and Havasupai Gardens, where topography and diameter limitations make the flexible product suitable, Fleming says.
Slip will be used where feasible, but many sections of existing pipe cannot accommodate the method due to small diameters and excessive bends.
One of the major challenges of the project is the topography. Remote job locations require crews to work in conditions that differ significantly from regular construction sites. Many work areas are several miles from the trailheads, and teams must come in and out daily unless they are staying at Phantom Ranch or other designated areas. Many work areas are narrow, steep and only accessible by rope systems or narrow ledges.
“In traditional projects, all utilities are installed in the same trench at the same time,” says Fleming. “Here, canyon limitations prevent that. Each utility requires separate excavation.”

Much of the pipeline is being placed in remote areas that have no place for helicopters to land or for crews to stage equipment.
Photo courtesy of nps.gov
Accessibility logistics
Since most of the sites are only accessible by air, helicopter operations are crucial to the project. High-performance helicopters fly daily cargo flights to transport pipelines, equipment and supplies to remote locations in the canyon that have narrow corridors, variable winds and limited landing areas.
Weather conditions, including strong winds and sudden storms, can stop flights at short notice. Extreme heat is another factor. Summer heat in the inner canyon can exceed 110°F, while winter conditions in the rims can bring snow and ice. Work hours are seasonally adjusted to account for these variations.
The protection of the environment and cultural resources also influences construction. Crews must minimize soil disturbance, avoid sensitive areas, and coordinate with park staff to maintain visitor access to heavily used trails.
And then there’s the geology of the canyon, which adds another layer of complexity. Rock types vary significantly along the route, requiring crews to adapt excavation methods as they move through different formations. Some areas allow shallow trenches to be dug, while others require hand tools or small equipment dropped by helicopter.
.jpg)
Image courtesy of nps.gov
Click on the image for more detail
Financing and delivery of projects
The TCWL replacement is funded through the Great American Outdoors Act and the Federal Lands Recreation Enhancement Act. NPS leadership says the project addresses long-standing infrastructure needs that were previously deferred due to funding constraints.
“This major undertaking is an example of the work taking place in national parks across the country to repair or replace vital infrastructure,” NPS Director Chuck Sams said in a statement. “Bipartisan commitment to funding sources is really making a difference.”
The new water supply system is expected to significantly reduce emergency repairs and operational disruptions once it is online. By removing the most failure-prone sections of the existing pipeline and replacing aluminum with steel, NPS aims to improve system reliability and reduce maintenance costs.
The redesigned dam at Bright Angel Creek will shorten the pipeline by about seven miles, eliminating the segment with the highest number of breaks. The new steel pipe is designed to withstand high environmental pressures and stresses.
NPS officials say the project will protect natural and cultural resources, maintain the visitor experience and provide reliable water service for the next 50 years or more.
With construction approximately 70% complete, crews will continue to install steel pipe along the remaining sections of the canyon’s inner corridor, advance work on the two water treatment plants and complete the helibase operations building. Additional phases of trench, slip, and conduit installation will continue through 2026. Final testing and certification of the system will occur in 2027, when the project is officially turned over to NPS.
