Close Menu
Machinery Asia
  • Home
  • Industry News
  • Heavy Machinery
  • Backhoe Loader
  • Excavators
  • Skid Steer
  • Videos
  • Shopping
  • News & Media
Facebook X (Twitter) Instagram
Facebook X (Twitter) Instagram
Machinery Asia
Subscribe
  • Home
  • Industry News
  • Heavy Machinery
  • Backhoe Loader
  • Excavators
  • Skid Steer
  • Videos
  • Shopping
  • News & Media
Machinery Asia
You are at:Home » Developers of $11.6 million Golden Pass LNG seek 3-year extension
Industry News

Developers of $11.6 million Golden Pass LNG seek 3-year extension

Machinery AsiaBy Machinery AsiaSeptember 10, 2024No Comments2 Mins Read
Facebook Twitter Pinterest LinkedIn Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email Tumblr

This audio is automatically generated. Please let us know if you have any comments.

Dive Brief:

  • The developers of the $11.6 billion Golden Pass liquefied natural gas export project in Texas have requested a three-year extension to complete construction, citing delays caused by the bankruptcy filing of the main construction contractor, according to documents filed with the Federal Energy Regulatory Commission on Aug. 28 .
  • Former prime contractor Zachry Holdings filed for Chapter 11 bankruptcy protection in May, saying the megaproject was at least $2.4 billion over the original budget, hemorrhaging money. The contractor has had years of disputes over costs, payments, layoffs and project delays with developer Golden Pass LNG Terminal LLC.
  • Golden Pass LNG is formed by joint developers Qatar Energy and ExxonMobil, which respectively have a 70% and 30% stake in the methane gas project. them reached an agreement with San Antonio-based Zachry Holdings allowed him to exit the project in July.

Diving knowledge:

The developers requested an extension to build and commission the facility by November 30, 2029. The project was originally scheduled to enter service in December 2021, and then got an extension to finish the works in November 2026.

In the latest extension request filed with FERC, the developer said schedule uncertainties related to the transition to a new prime contractor mean the project needs more time and cited “other potential delays beyond the control of GPLNG that may occur, such as potential hurricane impacts, and for start-up and commissioning activities, this additional time is necessary to complete construction of the project and bring it into service.”

The company intends produce the first LNG around the end of 2025, with commercial operations following, a Golden Pass LNG spokesman told Reuters, with additional time built in for contingencies.

The Golden Pass project is located in Port Arthur’s Sabine Pass neighborhood on the site of a former import terminal that was converted to process methane gas for export, according to Reuters. It has an annual export capacity of approximately 18 million tons.

The project was initially estimated to cost $9.25 billion in 2019, but that skyrocketed by 25% in August 2022 due to COVID-19 and geopolitical issues.

Source link

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
Previous ArticleWhy buying a minicar is a smart investment for long-term savings
Next Article Delivery Excavator CASE CX210C baru buka bungkus langsung main lumpur
Machinery Asia
  • Website

Related Posts

New York City shows updated sidewalk covers

June 18, 2026

2Q 2026 Cost Report: Compensation Increase Declines After 2023 High

June 18, 2026

Q2 2026 Cost Report: Steady Prices Seen in Used Machines as Manufacturers Continue to Absorb Tariff Costs

June 18, 2026
Leave A Reply Cancel Reply

  • Facebook
  • Twitter
  • Instagram
  • Pinterest
Don't Miss

New York City shows updated sidewalk covers

2Q 2026 Cost Report: Compensation Increase Declines After 2023 High

Q2 2026 Cost Report: Steady Prices Seen in Used Machines as Manufacturers Continue to Absorb Tariff Costs

Q2 2026 cost report: Construction executive confidence unchanged despite conflict with Iran

Popular Posts

New York City shows updated sidewalk covers

June 18, 2026

2Q 2026 Cost Report: Compensation Increase Declines After 2023 High

June 18, 2026

Q2 2026 Cost Report: Steady Prices Seen in Used Machines as Manufacturers Continue to Absorb Tariff Costs

June 18, 2026

Q2 2026 cost report: Construction executive confidence unchanged despite conflict with Iran

June 17, 2026
Heavy Machinery

Why dump trailer maintenance is important for long-term use

June 17, 2026

Top 5 Trailer Safety Mistakes to Avoid Before Towing

June 11, 2026

How to Choose a Gooseneck Tilt Equipment Trailer for Your Business

June 8, 2026

As a double-axle tilting trailer facilitates the transport of vehicles and equipment

June 5, 2026

Subscribe to Updates

Get the latest creative news from FooBar about art, design and business.

Type above and press Enter to search. Press Esc to cancel.