The Perini tutor has put a price and a timeline New York City Prisons Project Manhattan.
The Los Angeles-based megaproject contractor announced the price of work on February 19-3.8 billion-and said that the contract documents with the city’s design and construction department ended.
The contract contains 2,646 calendar days – or seven years and three months – for the final completion of the project, according to the statement. Will be located at 124-125 White Street in the Baix Manhattan Chinatown district City project website. This is the old place of the Manhattan detention complex, which was also known as “the tombs” before it was demolished in 2023.
The scope of the new prison project includes the design and construction of an installation with space dedicated to on -site services and programming, interior and exterior recreation, food services, offices and staff facilities , services and an insured entrance, according to the Perini tutor.
The new installation will contain 1,040 beds and provide 125 accessory parking spaces below the degree for all staff and service providers. In addition, the ground floor will contain 20,000 square feet of commercial and commercial space.
Tutor Perini announced in November that his joint company with Torrington, based on Connecticut, had appeared as industries The apparent winner of the jobAlthough he did not put any value to him. Tutor Perini will be the manager of the project, with O&G as a member of 25%. The Hok Architecture Firm is the prison design partner.
The installation is one of the four of New York City is building to replace its notorious Riker prison, which is expected to be closed by 2027, although it is unlikely that the deadline will be unlikely, unlikely, According to the New York Times. By 2023, Tutor Perini also won the job at Build Brooklyn prison of $ 2.95 million.