Close Menu
Machinery Asia
  • Home
  • Industry News
  • Heavy Machinery
  • Backhoe Loader
  • Excavators
  • Skid Steer
  • Videos
  • Shopping
Facebook X (Twitter) Instagram
Facebook X (Twitter) Instagram
Machinery Asia
Subscribe
  • Home
  • Industry News
  • Heavy Machinery
  • Backhoe Loader
  • Excavators
  • Skid Steer
  • Videos
  • Shopping
Machinery Asia
You are at:Home » Project of the Year and Best Project, Energy/Industrial: South Fork Wind
Industry News

Project of the Year and Best Project, Energy/Industrial: South Fork Wind

Machinery AsiaBy Machinery AsiaNovember 11, 2024No Comments6 Mins Read
Facebook Twitter Pinterest LinkedIn Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email Tumblr

South Fork Wind

East Hampton, New York

BEST PROJECT, ENERGY/INDUSTRIAL


KEY PLAYERS

Sent by: Eversource Energy

Developers: Eversource Energy; Ørsted

Leading design companies (onshore): HDR and TRC Cos.

General Contractor (Onshore) | Installation of conduit banks and substation: Haugland Group

Construction Manager (on ground): Burns and McDonnell

EPC contractor (offshore substation): Kiewit Offshore Services

Installation of cables (on the ground): LS Cable/Hawkeye

Cable installation (offshore): DON’T SAY

Horizontal directional drilling touched the ground: Michels

Secondary steel turbine: Riggs Distler

Installation of the turbine: Siemens Gamesa Renewable Energy

Turbine Basics: Boskalis




As the first utility-scale offshore wind project operating in New York and the US, South Fork Wind marks an important milestone in the transition to renewable energy. Located off the coast of Long Island in federal waters, the 130 MW project is designed to meet the area’s growing energy demands by producing clean energy for about 70,000 homes.

The project, which began construction in January 2022 and was commissioned in December 2023, was led by Ørsted Offshore North America, which developed the offshore infrastructure, and utility Eversource Energy, which led the effort on the ground.

“Customers were saying they want clean energy, and this was the way within our geography to make that happen,” says Julia Bovey, spokeswoman for Eversource. “For New England and the Northeast, offshore wind is our thing [opportunity]and we have to figure out how to use it.”

Project structures

The structures and materials for the project were stored and assembled at the New London State Pier in Connecticut.
Photo courtesy of South Fork Wind

The wind farm features 12 Siemens Gamesa wind turbines, each generating 11 MW, which were installed approximately 35 miles off the coast of East Hampton, NY. The turbines feed into a 500-ton, 60-foot-tall marine substation that was designed and manufactured by Kiewit. Offshore services at their facility in Ingleside, Texas, near Corpus Christi.

More than 350 workers from three states supported the construction of the structure. The substation was transported by barge across the Gulf of Mexico and up the East Coast for installation at the South Fork Wind project site. “Clean energy production is at a crucial stage in the US, and offshore wind, like the South Fork Wind project, has a very important role to play,” says Paul Geldmeier, who leads the wind energy work marina de Kiewit as executive vice president of its energy unit.

The project provides power through a single 138 kV transmission line connected to the East Hampton substation. A 68-nautical-mile submarine cable stretches from the wind project site to its grave beneath Wainscott Beach in East Hampton.

installation of turbine blades

Crews install the turbine blades at sea.
Photo courtesy of South Fork Wind

Effort on the ground

The scope of the project on land proved to be a critical phase for South Fork Wind to meet its goal of supplying power to the grid by 2023. A 40-acre terminal in the port area of ​​New London, Connecticut, had a $250 million renovation. as a place of assembly and organization of the project. It is also scheduled to serve Orsted’s 920 MW Sunrise Wind and 704 MW Revolution Wind projects.

Transparent and frequent communication between various teams and stakeholders was critical to the project, says the award presentation. Weekly communication with residents and local leaders through media and social media helped address concerns and maintain community support. Weekday ground construction was limited to a 7am to 7pm window with limited weekend work. In some high-traffic areas, such as roads and beaches, no work has been carried out during the seasonal period from May to September.

The team ensured that all homes along the route and access point to the local beach were accessible to homeowners and beachgoers. Traffic could only be stopped temporarily to ensure safe working conditions. As additional protection, temporary sound walls were installed as needed. Complying with local, state and federal permitting requirements was another critical part of the project. The submission cites teamwork and ongoing communication with regulators as needed to navigate the complex enabling landscape effectively, remain compliant and avoid delays.

One of the most complex aspects of the project was the offshore to onshore transition, where horizontal directional drilling was required to connect the offshore and onshore transmission systems. Crews installed a cable approximately 80 feet below the beach to protect the infrastructure from erosion and storm impacts. The technical complexities and environmental considerations of drilling required meticulous planning.

giant turbine blades

The project team loaded giant turbine blades into the assembly site in New London.
Photo courtesy of South Fork Wind

meeting point

A joint transition bay was where the Ørsted and Eversource project areas were connected. “At the transition interface point, we had to coordinate our designs, cable testing, and all the different phases of construction that span the ground,” says Burns McDonnell Project Manager Vinny Montemurro, who served as project manager programs on the South Fork beginning in 2018 with an additional construction management role in 2020.

The construction took about 16 months from the opening to the resurfacing of the roads. Ground transmission construction included a 4.1-mile cable route to a new ground substation. The trench was used to install underground cable infrastructure along the overland route. During trenching, areas up to 600 feet in length were opened up, then filled and patched once the infrastructure was established. The cable was pulled through the conduit bank system at each vault location.

Ground work was done with union labor, with an emphasis also on using local companies and M/WBEs, the team says. “The completion and full integration of South Fork Wind positions New York as a national leader in climate initiatives,” Gary LaBarbera, president of the New York State Building Trades, said in a statement. The project had no recordable incidents or accidents with 233,081 hours of work lost. Eversource says the knowledge and experience gained with South Fork Wind has been shared “across the industry, driving innovation and paving the way for future projects.”

Gov. Kathy Hochul (D) said the project represents progress toward the state’s goal of developing 9 GW of offshore wind power by 2035. “This milestone highlights the tremendous opportunity we have to create a new industry from the ground up to boost our green energy economy,” he said in a statement.

[Editor’s note: Eversource Energy in October completed the sale of its 50% interest in South Fork Wind and Revolution Wind to Global Infrastructure Partners. The latter project is set to serve Rhode Island and Connecticut by 2026. Eversource remains a tax equity investor in South Fork Wind and is a contractor on Revolution Wind for onshore construction.]

Source link

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
Previous ArticleAward of Merit, Interior Improvement/Tenant: Grand Seiko Flagship Boutique
Next Article November 2024 City Scoop: Providence
Machinery Asia
  • Website

Related Posts

Partial federal shutdown extends through Tuesday, House Speaker says

February 2, 2026

Under the data center boom

February 1, 2026

Prices of construction materials fell slightly in December, but were still up from more than a year ago

January 31, 2026
Leave A Reply Cancel Reply

  • Facebook
  • Twitter
  • Instagram
  • Pinterest
Don't Miss

Partial federal shutdown extends through Tuesday, House Speaker says

Under the data center boom

Prices of construction materials fell slightly in December, but were still up from more than a year ago

Court rules Cook County misused $243 million in transportation funds

Popular Posts

Partial federal shutdown extends through Tuesday, House Speaker says

February 2, 2026

Under the data center boom

February 1, 2026

Prices of construction materials fell slightly in December, but were still up from more than a year ago

January 31, 2026

Court rules Cook County misused $243 million in transportation funds

January 31, 2026
Heavy Machinery

Car hauler trailer kit basics for real world towing

January 26, 2026

Hydraulic tilting gooseneck trailer for transporting heavy equipment

January 26, 2026

Aluminum car trailer with tilt bed explained for real world vehicle transport

January 26, 2026

What is the best cover for a car trailer?

January 23, 2026

Subscribe to Updates

Get the latest creative news from FooBar about art, design and business.

Type above and press Enter to search. Press Esc to cancel.