Femern A/S just released this nice photo of Boskalis’ giant Odin backhoe dredger.

Odin arrived in Rødbyhavn at the end of May, with the task of carrying out a very important task of removing the outer and temporary seawall at the Fehmarnbelt tunnel.
The temporary dike has protected the water tunnel portal work so far.
“But since the entrance to the tunnel portal is now under water and we have completed the 200 meter wide permanent seawall, the outer and temporary seawall is no longer needed and can therefore be removed.,” he said Fehmarn.
Construction of the tunnel started in 2020 on the Danish side and in 2021 on the German side.